| Client |
St Ives Gold Mine |
| Location |
Kambalda - Western Australia - Western Australia |
| Requirement |
Complete full clean of process plant thickener utilising the hydromining process |
| Product |
Gold processing slimes and fines |
| Equipment |
- Hydromining towers x four, booster
- pump, 3 inch water cannon, underside
- discharge pump, high pressure hose,
- general spooling, mobile workshop
|
| Additional Equip |
- REL Support Vehicles, flow metre, bulk
- bunded fuel tanks
|
| Services Provided |
REL provided a complete thickener clean utilising the hydromining method along with highly trained crew to carry out the task. This project was conducted using day and night shift. Complete engineering design and methodology of Hydromining circuit. |
| Since |
|
| Contract |
|