| Client |
Consolidated Minerals Ltd |
| Location |
Woodie Woodie - North West Australia - Western Australia |
| Requirement |
To supply 2.5mw of continuous, uninterrupted power for 24 hour, 7 days a week mine water management system |
| Product |
Power generation |
| Equipment |
- 2 x 750 kva Prime Power Super Silent
- Generators and 2 x 550 kva Prime Power
- Super Silent Generators complete with
- Auto Start, Auto-sync and Load Sharing
- Equipment
|
| Additional Equip |
- 1 x 415 volt ip56 rated power management &
- distribution equipment. 2 X 415 volt to 11,000
- volt step up transformers, 2 x 11,000kv
- ring main units down to in pit with 2 x skid
- mounted, blast protected 11,000kv to 1,000
- volt step down transformers
|
| Services Provided |
This was a purpose built design, from concept through engineer, built, supply, install, commission and maintain a system to supply continuous and uninterrupted power for 1,000 volt fully integrated mine water management system |
| Since |
2009 |
| Contract |
Ongoing |