REL

Temporary pit dewatering pontoon pump system and booster pumps

Project Profile

Download PDF Project Profile
Client Alacer Gold
Location Higginsville, Goldfields - Western Australia - Western Australia
Requirement To dewater chalice pit (200lt/sec @ 200m TDH)
Product Mine and rain water
Equipment
  • 2 x 220kW 1000v pontoon pumps
  • 2 x 250Hp Diesel driven trailer mounted transfer pumps
  • 1 x 750kVA diesel generator set
Additional Equip
  • 2 x 55,000 Litre bulk diesel fuel supply
  • tanks – diesel pump and generator remote
  • fuel supply system spools, manifolds and all
  • associated tie-ins
Services Provided Engineering, design, installation, commissioning and decommissioning as well as transport of HDPE and pumping system and full design of pipe system
Since 2011
Contract 6 months